Project Overview
Project Overview
The project has 107 MWp of DC capacity and 82.5 MW of AC capacity, with a new 110 kV step-up substation and one 110 kV grid connection line.
Power is collected through 35 kV circuits to the new 110/35 kV substation. The substation includes one 100 MVA main transformer and outdoor 110 kV switchgear in a line-transformer unit arrangement.
Hubei Haiwen provided technical services appropriate to the project type. The information shown here is limited to disclosed project materials and does not extend beyond publicly available contract scope or delivery outcomes.